Supporting the redevelopment of a live A&E department

To enable the transformation of the A&E department at Royal Shrewsbury Hospital, WysePower were appointed to deliver the electrical infrastructure, mains distribution, and a range of temporary site services.

The ambitious redevelopment was delivered under the Integrated Health Projects Frameworks (IHP) in partnership with Vinci Construction and represents a key investment in emergency care for the region.

Scope of works

WysePower’s early involvement began during the pre-construction and bid stages, where the team supported Vinci Construction with costs and design details to secure project approval.

Following a successful bid, the initial phase of works began to remodel the existing A&E facilities. WysePower installed small power systems to maintain operational continuity and supplied temporary power and lighting during ward configurations. In addition, the team also completed the electrical setup for welfare cabins and temporary accommodation units.

Once the project had progressed into the main construction phase, WysePower established a comprehensive mains power distribution system and lighting and tower crane supplies across the site. The team is also providing infrastructure to support modular welfare and office facilities.

Working in a live environment

WysePower’s biggest challenge was carrying out enabling works within a live hospital environment. The project presented significant logistical challenges as the team had to work in extremely limited space due to the day-to-day continuous activity in the hospital and restricted access caused by full parking areas.

“To overcome these challenges, we had to meticulously plan and coordinate our activity to ensure the safety of patients and staff,” said Andy Roberts, Sales & Estimating Manager – Midlands & South. “In that part of the country, you have Telford and Shrewsbury and there’s only two hospitals in the area, so it gets very busy.

“Logistically, it was difficult to get started, but it’s been a very rewarding project, and we’ve enjoyed working on it.”

Strengthening client relationships

The established relationship between WysePower and Vinci Construction/IHP was a key element to the project’s success, having worked together previously on several projects in the UK.

“We’ve worked with IHP on several major hospital projects in the South-West, including Royal Bournemouth Hospital. Some of our team at Shrewsbury have also worked with Vinci Construction on other projects, so we already had strong relationships in place. That familiarity made collaboration easy from the start. Our ongoing work with Vinci and IHP is built on that same trusted relationship.”

All major electrical infrastructure is now in place and construction is progressing on schedule.