WyseBase: stabilising success for a temporary school
To support the construction of the Oasis Academy project, WyseBase was appointed by main contractor The McAvoy Group to deliver temporary foundations that were easy to install, capable of handling heavy loads, and could withstand challenging ground conditions.
The Oasis Academy project is a temporary school, which allows students to continue learning while the permanent structure is currently under construction on a different site.
Securing temporary foundations
McAvoy initially hired WyseBase to set up the access steps and ramps, but following site visits and conversations between both teams, WyseBase were appointed to install temporary foundations.
“McAvoy were constructing their own concrete foundations at the start, which brought some complaints, and there were issues with the local council, so I started to talk to the team about our foundation system and how it would be more convenient for them,” said Mike Collier, WyseBase Regional Manager. “Unlike traditional concrete foundations, our WyseBase foundations don’t require excavation, levelling, or curing time. They can withstand heavy loads and are fast and easy to install.”
First-time use
Due to the scale of the site, larger foundations were needed to support the temporary structures. The team installed the bigger 1320 x 1320 mm bases – used for the first time on this project. “The ground conditions were challenging, but the larger bases helped us cover more ground,” continued Mike. “The Oasis Academy project is probably the first time we’ve installed WyseBase on such a vast scale.”
A challenging site
The quality of the ground proved to be a major challenge for the team, thanks to the uneven surfaces and weak soil conditions. The site is also in proximity to a main road and fall away embankment, so careful planning was required to get the ground ready to lay the foundations safely and efficiently.
“The ground conditions of the site presented significant challenges from the outset,” explained Mike. “The land had previously been used as a traveller site and was in a rundown state. Our modular foundation system helped stabilise the temporary structures without further disturbing the ground.”
Start of a great relationship
“We’ve built a good relationship with McAvoy,” continued Mike. “This is the first time we’ve worked with them, and they’ve been extremely happy with the results. They kept coming back to us when a new phase of the project started and we’ve also had some other separate projects from them, so this has been a fantastic job to work on.”
The project is due for completion in 2027.