Flying high: WysePower delivers first-class service at Manchester Airport

Manchester Airport is undergoing an ambitious transformation to improve capacity and modernise facilities. The £1.3 billion 10-year investment programme involves the closure of Terminal 1 to make way for a two-terminal system, Terminal 2 (T2) and Terminal 3 (T3), that will offer new security upgrades, seating, and a 500-seat bar.

Wysepower got off to a flying start when it was appointed to deliver a range of temporary electrical services as part of the transformation.

Scope of works

The project included the refurbishment of the existing T2 terminal and the construction of a new extension, which involved working with multiple contractors. The team worked with Mace Group on the T2 and P2 (new wing) refurbishments and BAM Construction on the internal works, such as the departure lounge.

WysePower provided a complete temporary power and lighting package, which included lift supplies, transformers and setting up power supplies to temporary fire alarms.

Flexible lighting solutions

A key element of the works included the installation of temporary lighting infrastructure, including high-level floodlights on the airfield to support safe operations throughout the project.

“We installed temporary lighting on the airfield using 3.2-tonne precast concrete bases, which provided a stable foundation for the lighting columns without the need for permanent ground fixings,” said Josh Ledger, Contracts Manager. “Because it’s an extremely busy site, having this flexible system ensured constant, reliable lighting with minimal disruption.”

Working on a live, secure site

The airport remained opened during refurbishment, which posed significant logistic challenges, Airside access was limited and all materials and personnel were required to pass through strict security procedures.

“The main difficulty was organising materials and getting everything through security at the right time,” continued Josh. “Everything had to be booked in advance, and every time you went in or out you had to go through scanners.”

Keeping the project moving

 

On-site work was fast-paced and required careful coordination among multiple contractors to meet the project’s demands.

Josh concluded: “It was all about keeping things moving and responding quickly when needed. We have a good relationship with all the clients, so we were able to work through any challenges together.”

The extension to Terminal 2 opened in 2021, and the original terminal building is now in the final stages of refurbishment.