High-rise living: WysePower supports landmark build with temporary site service
WysePower was appointed by Berkeley Group to deliver a range of temporary services across phases 1, 2 and 3 of a major landmark residential development in the heart of Islington.
250 City Road is currently undergoing a major regeneration. The site is being transformed from a neglected business park to a thriving residential community, incorporating ground-floor commercial units and 1.9 acres of landscaped gardens and courtyards. Situated in a prime location between Angel and Old Street Stations, the development includes two residential towers of 42 and 36 storeys – where WysePower worked with the contractor to plan, design and carry out temporary electrical works.

“It was a great project win for us, and it was our first time working with Berkeley Group,” said Shaun Byron, Regional Director for London. “The client brought us in early – which is where we are most effective – working with us to plan the enabling services across their site. Due to the timing, we were able to design the most sustainable and cost-effective design, which was futureproofed against additional required and unforeseen service add-ons. Since City Road, we’ve been contracted by Berkeley Group for around 20 projects.”

Scope of works
The team undertook the complete design and installation of both low voltage (LV) and high voltage (HV) systems, including a 1400A switchgear with multiple sub-mains. Power was also supplied to three cranes on-site.
Additionally, the team also supplied to welfare facilities for high-spec cabins during phase one and completed small fit out works.
WysePower initially began work on phase one of the project in 2016. Following the success of works carried out during this phase, the contractor then negotiated for WysePower to continue supplying site services for phase two.
“Berkeley Group were really impressed with the excellent job the team were doing, and they wanted to continue working with us.”
Working around the challenges
The key challenge of the project was coordinating enabling works following the completion of phase one, as the site was already occupied by residents.
“As part of the enabling works, we had to run cables through the car park, but we had to be very careful as there were a lot of luxury cars so had to be very considerate of our surroundings.”
Additionally, nighttime operations meant the team needed to complete some works at night, which meant noise had to be kept to a minimum – a difficult task where drills are involved.
“To get around this, the team had to ensure quieter working protocols, which included chalk-marking and restricted drilling windows to avoid disturbing the residents.”

Helping to support the next generation of WysePeople
For a project of this calibre, it was essential that in-house staff and high-quality equipment were always on-site to ensure WysePower’s temporary services were always available. A full-time supervisor and an apprentice were continuously on-site ensuring the project remained on track and were ready to tackle any issues that arose.
Having an apprentice on-site of a major project is not new. WysePower is committed to developing new talent through training, mentoring and hands-on development. A legacy of the City Road project is that the apprentice will have morphed into a fully qualified electrician once construction has completed.
“I’m always keen to get an apprentice on-site from day one,” continues Shaun. “Firstly, they’ll know the job better than anyone else because that’s the only site they’ll go to, and secondly, they’ve got pretty much one-on-one tuition from the electrician or the supervisor in this case, so they have full-on, practical experience. It’s such a great feeling to be able train and nurture new talent in our line of work.”
Giving back to the community
In addition to the temporary works, WysePower also strengthened community ties. Over the course of the project, WysePower donated materials and labour for community events, which included supporting a local school and setting up a festive installation. “It’s always good to give back to the local community,” continues Shaun. “We were happy to donate our time and materials to keep local events running during the construction period.”
Although most of the works have been completed, the team are still currently involved on the project.