Supporting the build of a vital Border Control facility

WysePower was appointed to assist Kier Group in providing temporary site services and connections for a new Border Control facility in Holyhead, North Wales.

The multi-million-pound structure, approved by the Welsh Government, will provide an improved link between Ireland and the UK and is expected to create 700 jobs in the local area. The facility is being built on a 15-acre site in Anglesey, 1.7 miles from the Port of Holyhead and will include separate inspection areas for pests and disease. The inspection buildings will provide offices, staff welfare facilities and other amenities.

Providing the full package

WysePower provided a full suite of services and equipment to enable the construction of the new facility.

The team set up site generators, battery storage units and fuel management prior to temporary site power going live, allowing work to start straightaway. Water storage tanks were also set up before a temporary connection from Welsh Water was installed.

The package also included enabling works for site welfare, car charging, site power and lighting and mechanical works.

Additionally, the team provided temporary power, lighting, water and CCTV for the main works supplied for the new buildings. Specialist external lighting was also installed to reduce light pollution for the local wildlife and residents.

Remote connections

Due to the site’s remote location, a temporary electrical connection from SP Energy Network (SPEN) was installed from a pole-mounted transformer to reduce the amount of space required for a substation. Supplying water to the site also proved to be a challenge in the initial stages but was quickly resolved by the team.

“Given the project’s location and the lead-in time on the temporary water connection, we specified a larger 20,000L water tank to reduce the number of water deliveries that were made, which meant we also reduced the site’s carbon footprint and reduced traffic on the local roads,” said Ian Green, Operations Director.

“A comprehensive package was developed during the enabling works period, which allowed us to work closely with Kier Group and their supply chain throughout the project.”

Powering ongoing collaboration

“We have a great working relationship with the site team and developed this scheme long before works started,” explained Ian. “We have had previous experience with the site team working in the area so even though the project is located in a remote area, we were confident we could deliver.”

The new facility is still under construction.

The project is being delivered over a three-and-a-half-year construction programme and is expected to be completed in Spring 2027.