Setting up a reliable power source and distribution point is essential in providing demolition support and is reliant on the requirements of the site, duration of the project and what power equipment is needed. It is also important to consider the cost-effectiveness of powering the project, and any environmental impacts site demolition may have on the surrounding area. Each site has individual demands and challenges. Here’s our guide to everything you need to know.
Getting power to the demolition site
The main challenge is to get a reliable supply of power to site, especially if the electrical connection has been cut off. There are three main ways to supply power:
- Temporary builders supply (TBS)
- Generators
- Reinstatement of existing mains supply
Temporary builders supply
Demolition sites are often powered through a temporary builders supply (TBS). A TBS, sometimes referred to as temporary building supply, is a temporary power connection installed by a utility company, which involves digging into the street to access the electrical grid and setting up a dedicated connection for the site. This means a site can have a reliable source of power throughout the duration of the project. In addition to installing and connecting temporary electrical services to the TBS, WysePower is well versed in working with utility companies and managing the complete connection process.
Generators
If it’s not possible to get a grid connection on site, portable diesel or hybrid generators can be deployed to site. Although portable generators are self-sufficient, hire costs, maintenance and cost of diesel can make them more costly than using mains power. Additionally, they produce carbon emissions which makes them less environmentally friendly.
Reinstatement of existing mains supply
If a demolition site was previously connected to the mains power supply, then it can be a cost-effective and sustainable solution to reinstate and reconfigure that supply. It’s important to check the remaining electrical system is still and safe and compliant before power is reinstated, but this can often be the preferred and most cost-effective method.
WysePower is well versed in the discovery and assessment of existing power and our on-site audits will let you know the possibilities with your particular site.
Equipment for demolition support
All demolition sites require a range of equipment to operate from large or heavy machinery to power tools.
Large or heavy machinery
Most demolition sites require large, heavy machinery to complete works, this includes tower cranes and hoists, which are essential for lifting or lowering heavy materials – particularly for controlled demolition or if sections of a structure need to be removed. Breakers also rely on an interrupted power supply.
WysePower’s electrical engineers are experienced electrical planners and are able to identify the power requirements of your site. Depending on the amount of cranes, hoists and so on, we are best placed to deliver a cost effective solution for your demolition site and any bear in mind future increased usage requirements.
Power tools
Portable power tools such as drills, circular saws and sanders require transformers on site to convert power to 110V. 110V power tools are the standard for construction sites because they help to enhance safety.
For example, if a 110V cable is cut accidently, then there is less risk of severe injury because the voltage is lower than in 240V tools, which are typically used in home applications. However, it’s important to check with the site manager that your tools comply with the requirements before you start work.
On-site lighting
It’s essential that all construction and demolition sites have adequate lighting and it’s required by law under the Health and Safety Act 1974, to ensure that the site runs effectively and that workers can complete their tasks safely.
Lighting systems on demolition sites typically follow a two-phased install. Phase one is the enabling set-up, where a basic, but effective lighting package is installed to allow site workers to complete their tasks safely. Once this has been completed, phase two begins. Phase two is where the project moves into the fit-out stage and there would be an increase in lighting quantities and qualities. WysePower has a lighting solution to suit each phase, ensuring the correct lumen readings are installed across the site.
Portable tower lights, task lights and flood lights are some of the most common types of lighting on construction sites. LED lights are a popular choice for construction sites as they are more energy efficient. They use 90% less energy and produce less heat than traditional bulbs.
Read our guide to construction site lighting.
Fire safety and site security systems
Ensuring fire safety is crucial. Demolition sites are high risk areas due to the building types (often older or heritage in some cases), type of materials and tools on site. Following major fires, such as the incident at the Glasgow School of Art, strict fire regulations are in place. Temporary fire alarms must include detection systems that work outside of working hours to prevent undetected fires. Additionally, if the site is next to or attached to another building, the fire alarm must be able to trigger the adjacent property’s system to ensure a coordinated response.
It’s important to remember that insurance companies strictly enforce fire alarm regulations. If you fail to comply with the regulations, it can void your policy. WysePower can devise a fully compliant, tailored fire alarm system to suit your project requirements.
Read more about how the WysePower team improved fire safety while working on the Manchester Town Hall project.
Construction and demolition sites are also vulnerable to theft and criminal damage. Tool theft is a particular issue. According to a recent report, around 45,000 tool thefts were reported to the police in 2023, which was a 5% rise on the previous year. So, it’s important to have the right security systems in place.
What system you choose may depend on the size of your site or the duration of your project. Wireless alarms, CCTV and intruder alarm systems are commonly used on construction sites.
Powering site demolition with WysePower
As mentioned previously, the key to having an efficient demolition site is ensuring there is an efficient and consistent power supply, and that’s where WysePower comes in. We can devise a whole package of temporary power solutions – bespoke to your site’s requirements – and keep you connected throughout the duration of the project from start to finish.
Whatever your project needs, we have a wide range of temporary electrical equipment as well as temporary generators to keep your site powered. We’re also fully equipped for the installation of 110v and specialist transformers, and we have a huge stock of over 7,000 tested and compliant units.
We can also move quickly. Our expert teams will design, install and fully test all electrical equipment to get your site up and running as fast and efficiently as possible.
So, if you want to know about how we can help power your demolition site, why not get in touch by filling out the form below or give us a ring on 0808 168 1675.